Hawaiian Electric Preps Renewable Energy Solicitation

0

To continue progress toward achieving Hawaii’s clean energy goals, utility company Hawaiian Electric, whose subsidiaries include Maui Electric and Hawaii Electric Light, plans to seek new renewable energy projects for Oahu, Maui and Hawaii Island beginning in early 2018.

Earlier this month, the state Public Utilities Commission (PUC) granted the company’s request to start the regulatory process to issue requests for proposals (RFP) enabling the execution of a five-year action plan for more renewable generation.

To that end, the company says it has now filed with the PUC the proposed process for competitively procuring the largest amount of renewable resources ever to be developed in Hawaii. The filing includes drafts of proposed RFPs and a new model for renewable power purchase contracts.

The company is requesting stakeholder and market feedback on these draft documents over the next month to inform plans and to launch an expedited RFP process in 2018.

In line with the Power Supply Improvement Plan (PSIP) for Hawaiian Electric, Maui Electric and Hawaii Electric Light accepted by regulators in July, the company intends to issue RFPs in two stages over the next two years for renewable resources it targeted through 2022. Those resources include the following:

  • 220 MW of renewable generation for Oahu;
  • 100 MW for the island of Maui, including 40 MW of firm renewable generation; and
  • 50 MW for Hawaii Island

The company also intends to provide developers the option to include energy storage in their bids. The company says the two-stage RFP process is designed to expedite execution of the first stage so that developers can take advantage of investment tax credits before they expire, lowering costs for customers.

The new filing includes a proposed model contract between the company and developers of renewable projects. The PPAs are designed to address the unique challenges of operating island grids with high concentrations of renewables. Working with experts in the industry, the new model PPA seeks to achieve greater flexibility for utilities to dynamically and cost-effectively dispatch power from the new projects and to lower risks to developers and their financiers, resulting in lower costs to customers.

A new element of the proposed RFPs would require developers that advanced to negotiations to publicly engage with communities where their projects may be sited before a PPA is signed and again after an executed PPA is sent to regulators. This feedback will be submitted to the PUC as part of the contract review process. The company says it is now adopting this new requirement in its energy procurement process out of recognition that communities should have greater visibility into the process and have better engagement with developers.

“With the commission’s acceptance of our PSIP, we are entering a new period of renewable energy acquisition. We are now focused on creating and successfully executing a competitive process for renewable generation that will help achieve our vision for sustainable communities and result in cost competitive and reliable service to our customers,” says Shelee Kimura, Hawaiian Electric’s senior vice president of business development and strategic planning.

“This series of RFPs is a critical component of meeting Hawaii’s renewable energy goals and will require the coordinated efforts of many parties including developers, land owners, regulators, government entities and many stakeholders to make it a reality.”

The PSIP accepted by the commission describes key goals, such as seeking nearly 400 MW of new renewable resources by 2021. When the PUC opened the docket for this procurement process, it urged the company to move quickly on a “transparent, timely and successful procurement process” to work with developers and capture federal investment tax credits before they expire.

The draft RFPs and proposed PPA language are intended to meet the commission’s objectives. The company is also proposing a series of technical conferences and consultation with stakeholders, such as prospective renewable developers.

The proposed timeline calls for issuing the final RFPs in the first quarter of 2018, with selection of developers and contract negotiations expected to start in the second quarter. The draft documents, of primary interest to prospective renewable energy developers, may be reviewed here.

In December 2016, the company issued a request for information to landowners to identify land available for renewable energy projects. The results were provided to interested developers to help streamline the development process and facilitate the matching of sites and projects. This information continues to be available to interested developers at hawaiianelectric.com/landrfi.

Subscribe
Notify of
guest
0 Comments
Inline Feedbacks
View all comments